Pavement Management Program (PMP) Updates
Engineering Links
2024-101 PMP Street Improvement Project
82nd Street (12th Avenue to Old Cedar Avenue)
The Contractor paved the final layer of asphalt the week of October 21.
Dupont Area (W 84th Street, W 84 ½ St, Dupont Avenue)
The contractor paved the final layer of asphalt the week of October 21.
2021-301 American Blvd Curb Realignment
The contractor will be paving the street along with the asphalt trail adjacent to the property at 3701 American Boulevard the week of October 28
2024-102 PMP Street Maintenance Project
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will begin milling the existing asphalt the early the week of October 21st and will pave the site later in the week. The contractor will be in the week of October 21st restoring the site with topsoil and sod.
Chowen Area (Chowen Avenue, Beard Road, W 82nd St, W 93rd St, Ewing Rd)
The contractor will finish concrete work early the week of October 21st. The contractor will mill the existing asphalt late the week of October 21st and will pave the site early the week of October 28th.
2024-101 PMP Street Improvement Project
Bloomington City Council levied the 2024-101 Special Assessment Roll on October 14, 2024.
82nd Street (12th Avenue to Old Cedar Avenue)
The Contractor will be paving the final layer of asphalt the week of October 21.
Dupont Area (W 84th Street, W 84 1/2 Street, Dupont Avenue)
The contractor will be paving the final layer of asphalt the week of October 21.
2021-301 American Blvd Curb Realignment (part of the 2024-101 project)
The contactor will be installing the newly realign curb along the 3701 American Boulevard property the week of October 21.
2024-102 PMP Street Maintenance Project
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will begin milling the existing asphalt the early the week of October 21st and will pave the site later in the week. The contractor will be in the week of October 21st restoring the site with topsoil and sod.
Chowen Area (Chowen Avenue, Beard Road, W 82nd St, W 93rd St, Ewing Rd)
The contractor will finish concrete work early the week of October 21st. The contractor will mill the existing asphalt late the week of October 21st and will pave the site early the week of October 28th.
2024-101 PMP Street Improvement Project
A Public Hearing is scheduled for October 14, 2024, when City Council will consider the levy of the assessments.
82nd Street (12th Avenue to Old Cedar Avenue)
The Contractor will be paving the final layer of asphalt the week of October 21.
Dupont Area (W 84th Street, W 84 1/2 Street, Dupont Avenue)
The contractor will be paving the final layer of asphalt the week of October 21.
2021-301 American Blvd Curb Realignment (part of the 2024-101 project)
The contractor will begin work at 3701 American Boulevard the week of October 14 with work items such as traffic control devices installation and concrete curb and pavement removals. Utility pipes installation will follow later in the week.
2024-102 PMP Street Maintenance Project
W 78th Area (W 78th Street, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will finish installing the guardrail and will install permanent pavement marking the week of October 14th.
W Bush Lake Area (W Bush Lake Road, Utah Circle)
Asphalt paving is scheduled to be completed on Tuesday, October 15th.
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will begin installing concrete items including curb & gutter and sidewalk replacement the week of October 14th.
Chowen Area (Chowen Avenue, Beard Road, W 82nd St, W 93rd St, Ewing Rd)
The contractor will continue with improvement to the City-owned utilities the week of October 14th. The contractor will also being grading the site in preparation for concrete installation.
2024-101 PMP Street Improvement Project
A Public Hearing is scheduled for October 14, 2024, when City Council will consider the levy of the assessments.
82nd Street (12th Avenue to Old Cedar Avenue)
The Contractor will be paving the first layer of asphalt the week of October 7th
Dupont Area (W 84th Street, W 84 1/2 Street, Dupont Avenue)
The contractor has completed placement of the first layer of asphalt. They will be doing restoration and driveway paving through the week of October 7th. Paving of the final layer of asphalt is scheduled for the week of October 21st.
2024-102 PMP Street Maintenance Project
W 78th Area (W 78th Street, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will finish installing the guardrail and will install permanent pavement marking the week of October 7th.
W Bush Lake Area (W Bush Lake Road, Utah Circle)
The contractor will be milling the existing asphalt pavement the week of October 7th in preparation for final paving. The contractor will also being completing restoration of any disturbed areas with topsoil and sod the week of October 7th.
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will continue removing asphalt pavement and concrete curb. The contractor will also continue making repairs to City-owned utilities the week of October 7th.
2024-101 PMP Street Improvement Project
Assessment Informational meetings were held on September 24 and September 26 in the Public Works training room. A total of five property owners attended these meetings. A Public Hearing is scheduled for October 14, 2024, when City Council will consider the levy of the assessments.
82nd Street (12th Avenue to Old Cedar Avenue)
Concrete curb and gutter placement along with sidewalk installation is ongoing and will continue through the week of October 1. This work will be followed by final grading and paving of the first layer of asphalt the week of October 7.
Dupont Area (W 84th Street, W 84 ½ St, Dupont Avenue)
The contractor will be paving the first layer of asphalt the week of October 1.
2024-102 PMP Street Maintenance Project
W. 78th Area (W. 78th Street, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will be performing the asphalt milling the week of September 30th. The contractor will also be in the area beginning restoration activities including topsoil and sod on disturbed area.
W. Bush Lake Area (W. Bush Lake Road, Utah Circle)
The contractor will be installing concrete curb and begin grading in preparation for final paving the week of September 30th.
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will continue removing asphalt pavement and concrete curb. The contractor will also begin making repairs to City-owned utilities the week of September 30th.
2024-101 PMP Street Improvement Project
82nd Street (12th Avenue to Old Cedar Avenue)
All Testing requirements for the newly installed watermain are completed. The contractor will be finishing up subgrade preparation work late in the week of September 16. Concrete curb and gutter along with sidewalk on the south side of 82nd Street will be installed the week of September 23.
Emerson Area (Emerson Avenue, W 100th Street, Bloomington Freeway)
The final lift of asphalt will be paved late in the week of September 16.
Dupont Area (W 84th Street, W 84 ½ St, Dupont Avenue)
Concrete curb and gutter work in ongoing. The contractor will begin subgrade preparation the week of September 23, in anticipation of paving the first layer of asphalt the week of October 1.
2024-102 PMP Street Maintenance Project
W. 78th Area (W. 78th Street, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will continue installing new concrete curb and concrete sidewalk the week of September 23rd.
Ensign Area (Ensign Road, Ensign Curve)
Asphalt paving will be completed by Friday, September 20th.
W. Bush Lake Area (W. Bush Lake Road, Utah Circle)
The contractor will begin making repairs to City-owned utilities the week of September 23rd.
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will mobilizing into the site the week of September 23rd. The contractor will begin removing asphalt pavement and concrete curb.
2024-101 PMP Street Improvement Project
82nd Street (12th Avenue to Old Cedar Avenue)
Testing of the new watermain between 14th Avenue and Old Cedar Avenue is neighboring completion. Concrete curb and gutter along with sidewalk installation along the south side of 82nd Street is scheduled for the week of September 23
Emerson Area (Emerson Avenue, W 100th Street, Bloomington Freeway)
Boulevard restoration work and driveway paving are still ongoing. The contractor will be paving the final lift of asphalt the week of September 16.
Dupont Area (W 84th Street, W 84 ½ St, Dupont Avenue)
The contactor has begun removals the week of September 9, utility crews will be moving in later that week to perform storm sewer adjustment and reconstruction. Milling of the existing pavement and concrete curb and gutter work are scheduled for the week of September 16.
2024-102 PMP Street Maintenance Project
W. 78th Area (W. 78th Street, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will begin installing new concrete curb and concrete sidewalk the week of September 16th. Installation of the new guardrail and fencing along Normandale Service Road and Harmony Drive will be completed the week of September 16th.
Ensign Area (Ensign Road, Ensign Curve)
The contractor has a small amount of curb & gutter to replace early the week of September 16th. The contractor will be milling the existing asphalt and paving the final asphalt lift late the week of September 16th.
W. Bush Lake Area (W. Bush Lake Road, Utah Circle)
The contractor will mobilize into the site the week of September 16th. They will begin installing erosion control and saw-cutting pavement and curb. The contractor will also begin making repairs to City-owned utilities in the area.
Poplar Bridge Area (Poplar Bridge Road, Harrison Road, Harrison Circle, Poplar Bridge Curve)
The contractor will mobilizing into the site the week of September 23rd.
2024-101 PMP Street Improvement Project
82nd Street (12th Avenue to Old Cedar Avenue)
Testing of the new watermain between 14th Avenue to Old Cedar Avenue continues. Grading and installation of class 5 gravel will continue after the watermain testing is complete.
Emerson Area (Emerson Avenue, W 100th Street, Bloomington Freeway)
Paving of the first layer of asphalt will complete in the area late in the week of September 2. Boulevard restoration work will continue the week of September 9 with the final layer of asphalt anticipated to be paved the week of September 16.
Dupont Area (W 84th Street, W 84 ½ St, Dupont Avenue)
The Contractor is anticipating starting work in this area the week of September 16.
2024-102 PMP Street Maintenance Project
W 78th Area (W 78th St, Normandale Service Road, Glenroy Road, Harmony Drive)
The contractor will continue concrete curb and sidewalk removals throughout the area.
Ensign Area (Ensign Road, Ensign Curve)
The contractor will mobilize into the site the week of September 9th. They will begin making improvements to City-owned utility maintenance holes. The contractor will also remove select pieces of concrete curb & gutter for replacement.