Engineering Links
Pavement Management Program (PMP) Updates
![2016 PMP.jpg 2016 PMP Construction](/sites/default/files/styles/800x456/public/2016_pmp.jpg?h=c44fcfa1&itok=xJomVene)
2024-101 PMP Street Improvement Project
Meadowview Road (Old Cedar Ave to Old Shakopee Rd)
The Contractor is working on finishing the installation of curb and gutter this week. Paving of the first layer of asphalt and driveways restoration are scheduled for the week of July 1st.
Oakland Avenue (95th Street to 96th Street)
The contractor will be installing concrete curb and gutter late in the week of July 28. Tolerancing and paving of the first layer of asphalt are scheduled for the week of July 1st.
82nd Street (12th Avenue to Old Cedar Avenue)
The contractor will be putting out early notice signs along with inlet protection the week of July 1st. Traffic control devices will be installed the week of July 8th for work to begin the following week.
2024-102 PMP Street Maintenance Project
E. 86th Street (Portland Avenue to Bloomington Avenue)
The contractor will continue replacing concrete curb and concrete sidewalk panels the week of July 1st. The contractor will also begin adjusting maintenance access holes in preparation for asphalt milling and paving.
E. 92nd Area (W. 92nd Street, W. 93rd Street, Bryant Avenue, Aldrich Avenue)
The contractor will continue utility work the week of July 1st. The contractor will also begin removing and replacing concrete curb and concrete sidewalk.
2024-101 PMP Street Improvement Project
Penn Circle (Penn Ave to East Terminus)
Paving of the final layer of asphalt was completed early the week of June 17th. Traffic control devices are scheduled to be picked up the week of June 24.
Meadowview Road (Old Cedar Ave to Old Shakopee Rd)
Excavation of the street and subgrade corrections were completed the week of June 17. The contractor will be working on curb and gutter installation the week of June 24, with potential paving of the first layer of asphalt later that week.
Oakland Avenue (95th Street to 96th Street)
Driveway removals were completed the week of June 17. Pavement removals have been postponed to the week of June 24. This will be followed by storm sewer work, street excavation and class 5 gravel installation the week of July 1.
2024-102 PMP Street Maintenance Project
E. 86th Street (Portland Avenue to Bloomington Avenue)
The contractor will continue utility work in the week of June 24th. The contractor will also begin removing and replacing concrete curb and concrete sidewalk panels the week of June 24th.
E. 92nd Street (Portland Avenue to 12th Avenue)
Final paving is scheduled to be completed early the week of June 24th. This work is weather dependent and subject to change.
Penn Lake Circle (Penn Avenue to east terminus)
The contractor completed final paving.
Garfield Avenue (W. 86th Street to cul-de-sac)
The contractor completed final paving. Permanent striping is scheduled to be installed the week of June 24th.
E. 92nd Area (W. 92nd Street, W. 93rd Street, Bryant Avenue, Aldrich Avenue)
Work in this area is expected to begin the week of June 24th. The contractor will be setting up traffic control, saw-cutting, and beginning minor utility repair work.
2022-103 Lower Lyndale Ave Reconstruction
A preconstruction meeting was held and work is scheduled to begin mid-July.
2024-101 PMP Street Improvement Project
Penn Circle (Penn Ave to East Terminus)
Paving of the final layer of asphalt is anticipated to complete late in the week of June 10.
Meadowview Road (Old Cedar Ave to Old Shakopee Rd)
Pavement removals are complete and excavation of the street along with installation of class 5 gravel will continue the week of June 17. This will be followed by concrete curb installation.
Oakland Avenue (95th Street to 96th Street)
Pavement removals are scheduled to begin mid-late week of June 17. This will be followed by storm sewer work, street excavation and class 5 gravel installation the week of June 24.
2024-102 PMP Street Maintenance Project
E. 86th Street (Portland Avenue to Bloomington Avenue)
E. 86th Street road closure begins June 17th and will last approximately two weeks. The contractor needs to complete utility improvements across the roadway. A signed detour will be provided. Access to driveways will be maintained through the north-south cross streets.
E. 92nd Street (Portland Avenue to 12th Avenue)
The contractor will begin raising utility maintenance holes in preparation for final paving. Boulevard restoration will also occur the week of June 17th. Final paving is scheduled to be completed by Friday, June 21st. Final paving is weather dependent and subject to change.
Penn Lake Circle (Penn Avenue to east terminus)
The contractor will begin raising utility maintenance holes in preparation for final paving. Boulevard restoration will also occur the week of June 17th. Final paving is scheduled to be completed by Friday, June 21st. Final paving is weather dependent and subject to change.
Garfield Avenue (W. 86th Street to cul-de-sac)
The contractor will begin raising utility maintenance holes in preparation for final paving. Boulevard restoration will also occur the week of June 17th. Final paving is scheduled to be completed by Friday, June 21st. Final paving is weather dependent and subject to change.
2024-101 PMP Street Improvement Project
Meadowview Road (Old Cedar Ave to Old Shakopee Rd)
Pavement removals have started and will continue the week of June 10 along with storm sewer utility work. Excavation of the street along with installation of class 5 gravel will begin late in the week of June 10.
2024-101 PMP Street Improvement Project
Penn Circle (Penn Ave to East Terminus)
Concrete work will complete late in the week of June 3. Paving of both layers of asphalt along with boulevard restoration is scheduled for the week of June 10.