September 2014

September 26, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    The final layer of bituminous has been paved and striping is complete. The only remaining work other than punch list items is the installation of the signal system at 84th Street and Xerxes Avenue. The poles for this system are anticipated to be available in mid-late October.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Initial grading and placement of class 5 is complete. The Contractor has been granted a noise exception for Saturday, September 27 to start at 7am and plans to begin concrete work. Concrete work will continue early in the week of September 29. Final grading of class 5 is scheduled for late in the week of September 29 with paving of the first layer of bituminous to follow.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Paving of the first layer of bituminous is complete on Drew Avenue, Ewing Avenue and Baillif Place to Chowen Avenue. Bituminous driveway paving has started on these three streets and will complete early in the week of September 29. Pavement removals and storm sewer work in the remainder of the area is complete. Grading and placement of class 5 on Beard Avenue, Chowen Avenue and Abbott Avenue will continue the week of September 29 with concrete work to follow late in the week or the week of October 6. The Contractor has been granted a noise exception to begin work at 7am on Saturday, September 27 and plans to begin boulevard restoration in locations that curb and gutter has been placed.
  • Oxboro District Pedestrian Improvements (includes Lyndale Avenue from W 96th Street to south side of 9700 Lyndale Ave and W 96th Street from Lyndale Avenue to Aldrich Avenue)
    Existing sidewalk and bituminous removals are anticipated to begin the week of September 29 or October 6.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will finish work and turn on the signal at Little Road the week of September 29. Once work is completed on Little Road, the Contractor will begin signal work on Toledo Road. The steel for the Collegeview signals is scheduled to be shipped the end of the week of September 29. The signals are anticipated to be turned on mid-October.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will begin paving Monday, September 29 at 2 AM on Killebrew Service Road along with the entrances to the mall. They will begin paving Killebrew Drive Tuesday, October 30 at 4 AM and finish midafternoon. All work is weather dependent. Striping is scheduled for late in the week.
  • E. Old Shakopee Road (between 24th Avenue to 370' east)
    Paving is scheduled for early afternoon on Monday, September 29. All work is weather dependent. Striping is scheduled for late in the week.
  • Killebrew South Service Road
    The Contractor will begin paving Monday, September 29 at 2 AM. All work is weather dependent. Striping is scheduled for late in the week.
September 19, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)

    The final layer of bituminous is scheduled to be paved on Saturday, September 20 (weather permitting) under a full closure of W 84th Street from France Avenue to Washburn Avenue. The detour route will utilize France Avenue, American Boulevard and Penn Avenue. Xerxes Avenue will also be closed at W 84th Street with a detour that will utilize W 86th Street and Penn Avenue. The closure is anticipated to reopen by the late afternoon of September 20.

    The Contractor has been granted a noise exception for Saturday, September 20 to start at 7am for this paving. Striping is anticipated to occur the week of September 22.

  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    The final layer of bituminous has been paved. Punch list work remains.
  • 14th Avenue (between E 96th Street and E 98th Street)
    The final layer of bituminous has been paved. Punch list work remains.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Initial grading and placement of class 5 is anticipated to complete by the end of the day Fri, September 19. Concrete work is scheduled for the week of September 22.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Curb and gutter has been poured on Ewing Avenue, Drew Avenue and Baillif Place to Chowen Avenue with final grading and paving of the first layer of bituminous in this location scheduled for the week of September 22. The Contractor has been granted a noise exception to begin work at 7am on Saturday, September 20 and plans to pour curb and gutter on the remainder of Baillif Place from Chowen Avenue to Zenith Avenue. Pavement removals, storm sewer, grading and placement of class 5 will continue on Beard Avenue, Chowen Avenue and Abbott Avenue the week of September 22.
  • Oxboro District Pedestrian Improvements (includes Lyndale Avenue from W 96th Street to south side of 9700 Lyndale Ave and W 96th Street from Lyndale Avenue to Aldrich Avenue)
    The Contractor may begin saw cutting for removals the week of September 22. This project includes construction of a new sidewalk on the south side of 96th Street from Lyndale Avenue to Aldrich Avenue and on the west side of Lyndale Avenue from 96th Street to the south end of the 9700 property (Freeway Ford), as well as the installation of an enhanced crosswalk (flashing beacon system) at Lyndale Avenue and 96th Street along with a new transit shelter on the east side of Lyndale Avenue.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Signal parts for the Little Road have arrived and the Contractor will be finishing the signal work the week of September 22. The signal is anticipated to tested and turned on later in the week. Once the signal at Little Road is complete, the Contractor will work on the Toledo Road signal. The steel for the signal poles at Collegeview Road are anticipated to be shipped the last week in September. Once the poles are onsite, the Contractor will begin work.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will be milling September 22 and 23 starting at 5 AM both days. Once milling is complete, they will install temporary striping and begin raising iron. Paving is scheduled for September 29 and 30, with early morning starts.
  • E. Old Shakopee Road (between 24th Avenue to 370' east)
    The Contractor will be milling September 22 and 23 starting at 5 AM both days. Once milling is complete, they will install temporary striping and begin raising iron. Paving is scheduled for September 29 and 30, with early morning starts.
  • Killebrew South Service Road
    The Contractor will be milling September 22 and 23 starting at 5 AM both days. Once milling is complete, they will install temporary striping and begin raising iron. Paving is scheduled for September 29 and 30, with early morning starts.
September 12, 2014

2014-101 PMP Street Improvement Project

84th Street closure and detour W 84th Street will be closed from France Avenue to Washburn Avenue starting in the early AM on Saturday, September 20 (weather permitting) and reopening by the late afternoon. The detour route will utilize France Avenue, American Boulevard and Penn Avenue. Xerxes Avenue will also be closed at W 84th Street with a detour that will utilize W 86th Street and Penn Avenue. The Contractor will be paving the final layer of bituminous during the closure.

  • W 84th Street (between France Avenue and Washburn Avenue)
    The remainder of the concrete work and restoration in the area is nearly complete and will complete the week of September 15. The final layer of bituminous is scheduled to be paved on Saturday, September 20 (weather permitting) under a full closure of W 84th Street from France Avenue to Washburn Avenue. The detour route will utilize France Avenue, American Boulevard and Penn Avenue. Xerxes Avenue will also be closed at W 84th Street with a detour that will utilize W 86th Street and Penn Avenue. The closure is anticipated to reopen by the late afternoon of September 20. The only work that will remain other than final striping, is the installation of the signal system at 84th Street and Xerxes Avenue which will occur when the poles are delivered. This is anticipated to occur in October 2014. The intersection of 84th Street and Xerxes Avenue will remain at an all way stop until the signal system installation is complete.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Sod installation and raising of manholes and gate valves are complete. The final layer of bituminous is scheduled to be paved the week of September 15.
  • 14th Avenue (between E 96th Street and E 98th Street)
    Sod installation is anticipated to complete by the end of the day Friday, September 12. The Contractor plans to complete raising manholes and gate valves in the area early in the week of September 15 with paving of the final layer of bituminous to follow later in the week.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Storm sewer work is complete. Grading and placement of class 5 is scheduled to start early in the week of September 15.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Grading and placement of class 5 is complete on Ewing Avenue, Drew Avenue and Baillif Place to Drew Avenue. The Contractor has been granted a noise exception to begin work at 7 a.m. on Saturday, September 13 and plans to prep for curb and gutter placement and may begin pouring curb and gutter. Concrete work will continue in this area early in the week of September 15. Pavement removals, storm sewer, grading and placement of class 5 will continue on Baillif Place, Chowen Avenue and Beard Avenue the week of September 15.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Traffic signal work will continue at Toledo Road, Little Road and Collegeview Road the week of September 8. The Contractor is waiting for various parts for the signals.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will continue with removals in various locations the week of September 1 along with pouring curb and sidewalk and storm sewer work. The exiting left turn lanes and entrance lanes on 20th Ave (MOA Gate 2) will be closed until midafternoon Friday, September 12 for concrete work starting early Monday, September 8. The right out lane will be open along with the right in lane. Signing will be posted to direct traffic for these lane closures. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.
  • E. Old Shakopee Road (between 24th Avenue to 370' east)
    The Contractor will continue curb and sidewalk work in various locations the week of September 8. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.
  • Killebrew South Service Road
    The Contractor will continue curb and sidewalk work in various locations the week of September 8 along with storm sewer work. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.
September 5, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Traffic remains shifted to the center lanes of W 84th Street from Xerxes Avenue to France Avenue. Retaining wall installation on the north side of 84th Street at Xerxes Avenue is complete. The remainder of the concrete work is anticipated to complete the week of September 8. Restoration around the wall and the remainder of restoration along the corridor will follow the concrete work the weeks of September 8 and 15. The Contractor is anticipating paving the final layer of bituminous on September 20 (weather permitting) under a full closure of W 84th Street from France Avenue to Washburn Avenue. More information will be given when a schedule is determined. The only work that will remain is the installation of the signal system at 84th Street and Xerxes Avenue which will occur when the poles are delivered. This is anticipated to occur in October 2014. The intersection of 84th Street and Xerxes Avenue will remain at an all way stop until the signal system is complete.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    The final layer of bituminous has been paved. Punch list work remains.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Paving of the final layer of bituminous is complete. Punch list work remains.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Sod installation has started and is anticipated to complete by early in the week of September 8. Raising of manholes and gate valves will follow sod installation.
  • 14th Avenue (between E 96th Street and E 98th Street)
    The Contractor has been granted a noise exception for Saturday, September 6 to start at 7am and plans to continue boulevard restoration. The first layer of bituminous has been paved. Paving of bituminous driveways is anticipated to complete by early in the week of September 8. Boulevard restoration will continue the week of September 8 along with sod installation.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Storm sewer work has started in the area and will continue the week of September 8. Storm sewer work will be followed by grading and placement of class 5.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Storm sewer work is anticipated to complete on Ewing Avenue, Drew Avenue and Baillif Place up to Drew Avenue early in the week of September 8. Grading and placement of class 5 has started in this area and will continue the week of September 8.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Traffic signal work will continue at Toledo Road, Little Road and Collegeview Road the week of September 8. The Contractor is waiting for various parts for the signals.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    The Contractor will be finishing any remaining pavement markings and sodding/seeding the week of September 8 along with the installation of pedestrian push buttons at Humboldt.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    The Contractor will be finishing any remaining pavement markings and sodding/seeding the week of September 8.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    The Contractor will finishing any remaining sodding/seeding the week of September 8.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will continue with removals in various locations the week of September 1 along with pouring curb and sidewalk and storm sewer work. The exiting left turn lanes and entrance lanes on 20th Ave (MOA Gate 2) will be closed until midafternoon Friday, September 12 for concrete work starting early Monday, September 8. The right out lane will be open along with the right in lane. Signing will be posted to direct traffic for these lane closures. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.
  • E. Old Shakopee Road (between 24th Avenue to 370' east)
    The Contractor will continue curb and sidewalk work in various locations the week of September 8. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.
  • Killebrew South Service Road
    The Contractor will continue curb and sidewalk work in various locations the week of September 8 along with storm sewer work. Various lane closures will occur throughout the project. Temporary pedestrian routes will be setup where sidewalk work is being completed.

August 2014

August 29, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Traffic remains shifted to the center lanes of W 84th Street from Xerxes Avenue to France Avenue. Retaining wall installation on the north side of 84th Street at Xerxes Avenue is anticipated to complete by the end of the day Friday, August 29 (weather permitting). Restoration around the wall and the remainder of restoration along the corridor will occur the weeks of September 1 and 8. The Contractor is anticipating paving the final layer of bituminous in early-mid September and most likely on a Saturday under a full closure of W 84th Street from France Avenue to Washburn Avenue. More information will be given when a schedule is determined. The only work that will remain is the installation of the signal system at 84th Street and Xerxes Avenue which will occur when the poles are delivered. This is anticipated to occur in October 2014. The intersection of 84th Street and Xerxes Avenue will remain at an all way stop until the signal system is complete.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    The final layer of bituminous has been paved. Punch list work remains.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Raising of manholes and gate valves is complete. Paving of the final layer of bituminous is scheduled for the week of September 1.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    The first layer of bituminous has been paved along with bituminous driveways. Boulevard restoration has started and sod installation is anticipated to begin the week of September 1.
  • 14th Avenue (between E 96th Street and E 98th Street)
    Concrete work is complete. Grading of class 5 gravel is complete and the first layer of bituminous is scheduled to be paved early in the week of September 1.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Centerpoint Energy has finished there gas main relocation work in the area. Storm sewer work is scheduled to occur the week of September 1.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Pavement removal is complete on Ewing Avenue, Drew Avenue and Baillif Place up to Drew Avenue. Storm sewer work in the area of removal has started and is anticipated to complete early in the week of September 1. Storm sewer work will be followed by grading and placement of class 5 the week of September 1.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Traffic signal work will continue at Toledo Road, Little Road and Collegeview Road the week of September 1.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    Sodding/seeding is scheduled for the week of September 1 along with the installation of pedestrian push buttons at Humboldt.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    Paving has been completed. The Contractor will be striping the week of September 1 along with sodding/seeding.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    Paving has been completed. The Contractor will be sodding/seeding the week of September 1.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will begin curb and sidewalk removals in various locations the week of September 1. The exiting right turn lane on 20th Ave (MOA Gate 2) will be closed until mid-afternoon Friday, September 5 for concrete work. Various lane closures will occur throughout the project.
  • E. Old Shakopee Road (between 24th Avenue to 370' east)
    The Contractor will begin curb and sidewalk removals in various locations the week of September 1. Various lane closures will occur throughout the project.
  • Killebrew South Service Road
    The Contractor will begin curb and sidewalk removals in various locations the week of September 1. Various lane closures will occur throughout the project.
August 22, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Xerxes Avenue has been reopened to traffic at West 84th Street and the street has been reconstructed in that location with the first two layers of bituminous placed. Boulevard restoration and sod placement has started and will continue the week of August 25. Traffic has been shifted to the center lanes of West 84th Street from Xerxes Avenue to France Avenue. Retaining wall installation on the north side of 84th Street at Xerxes Avenue is anticipated to complete the week of August 25. The Contractor is anticipating paving the final layer of bituminous in early September. The only work that will remain is the installation of the signal system at 84th Street and Xerxes Avenue which will occur when the poles are delivered. This is anticipated to occur in October 2014. The intersection of 84th Street and Xerxes Avenue will remain at an all way stop until the signal system is complete.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    The final layer of bituminous has been paved. Punch list work remains.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Raising of manholes and gate valves is complete. Paving of the final layer of bituminous is anticipated to occur the week of August 25.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Sod installation is complete. Raising of manholes and gate valves has started and will complete the week of August 25. Paving of the final layer of bituminous is anticipated to occur the week of August 25.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    The Contractor plans to pave the first layer of bituminous early in the week of August 25. This will be followed by paving of the bituminous driveways and boulevard restoration.
  • 14th Avenue (between E 96th Street and E 98th Street)
    Pavement removal, storm sewer work and initial grading and placement of class 5 are all complete. Concrete work is anticipated to start on Fri, August 22 (weather permitting) and complete early in the week of August 25. The Contractor has been granted a noise exception to start of 7am on Saturday, August 23 and plans to continue concrete work (weather permitting).
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Pavement reclamation is complete. Storm sewer work has been slightly delayed to allow for CenterPoint Energy to relocate gas main in a few locations along the corridor. CenterPoint Energy is scheduled to do this work the week of August 25. Storm sewer work will follow gas main relocation.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    Tree removal has started and will continue the week of August 25. Pavement removal is scheduled to begin in the west end of the area the week of August 25 along with the start of storm sewer work.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Traffic signal work will continue at Toledo Road, Little Road and Collegeview Road the week of August 25.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    Paving will be complete Friday, August 22. Roadway is closed for paving and will be reopened once paving is complete. The Contractor will be striping the week of August 25. Seeding/sodding is scheduled for later in the week.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    The Contractor will be raising gate valves and manholes the week of August 25. Paving is scheduled for Thursday, August 28. Seeding/sodding will occur after striping.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    The Contractor will be raising gate valves and manholes the week of August 25. Paving is scheduled for Thursday, August 28. Seeding/sodding will occur after striping.
  • Killebrew Drive (between TH 77 ramp and Old Shakopee Road)
    The Contractor will begin construction the week of September 1.
  • East Old Shakopee Road (between 24th Avenue and 370’ east)
    The Contractor will begin construction the week of September 1.
  • Killebrew South Service Road
    The Contractor will begin construction the week of September 1.
August 15, 2014

2014-102 PMP Street Maintenance Project

84th Street closure and detour
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    W. 106th Street will be closed between Xerxes Avenue and Humboldt Avenue starting at 5 a.m. August 22 for paving with a detour provided that will utilize Humboldt Avenue, W. 100th Street, Old Shakopee Road and Xerxes Avenue. Paving is anticipated to be complete by mid afternoon August 22. The scheduled rain day is for August 23.
August 15, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    The first two lifts of bituminous have been paved in the Phase 2 area. Xerxes Avenue is currently closed at W 84th Street and is anticipated to reopen the week of August 18. The Contractor is reconstructing the south side of W 84th Street from Xerxes Avenue to Washburn Avenue during this closure. Concrete placement along with grading and class 5 placement have completed in this area and paving of the first two layers of bituminous is anticipated to complete by the end of the day Saturday, August 16 (weather permitting). The Contractor has been granted a noise exception for Saturday, August 16 to start at 7am and plans complete paving in the area and continue boulevard restoration. Traffic will be shifted to the center lanes of W 84th Street from Xerxes Avenue to France Avenue the week of August 18 to allow for boulevard restoration and sod/seed installation on both sides of 84th Street.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Sod installation is complete. The Contractor has started raising manholes and gate valves and will complete early in the week of August 18. The Contractor has been granted a noise exception for Saturday, August 16 to start at 7am and plans to continue raising manholes and gate valves in the area. The final layer of bituminous is anticipated to be paved the week of August 18 or 25.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Sod and seed installation is complete. The Contractor plans to raise manholes and gate valves the week of August 18.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Paving of the bituminous driveways is complete. Boulevard restoration has started in the area and will continue the week of August 18 along with sod installation. The Contractor has been granted a noise exception for Saturday, August 16 to start at 7am and plans to continue boulevard restoration.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Concrete work has started and will complete the week of August 18. The Contractor plans to continue grading and placing class 5 the week of August 18.
  • 14th Avenue (between E 96th Street and E 98th Street)
    Pavement and driveway removal has started in the area. Storm sewer work is scheduled for the week of August 18 followed by grading and placement of class 5.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Pavement removal is scheduled for Monday, August 18. Storm sewer work will follow later in the week of August 18.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    The Contractor anticipates starting tree removal in the area the week of August 18 with pavement removal starting the week of August 25.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be working on pavement markings the week of August 18. Traffic signal work will continue at Toledo Road, Little Road and Collegeview Road.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    The Contractor will be topsoiling the week of August 18. Milling is tentatively scheduled for Tuesday, August 19. Manholes and gate valves will be raised after milling. Paving is tentatively scheduled for Friday, August 22 with a rain date of Saturday, August 23. The road will be closed for paving starting at 5 AM between Humboldt Avenue and Xerxes Avenue. A detour will be set up to follow Humboldt Avenue, W. 100th Street, Old Shakopee Road and Xerxes Avenue. It is anticipated the roadway will be opened up mid-afternoon.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    The Contractor will be topsoiling and street patching the week of August 18. Milling is tentatively scheduled for Friday, August 22. Paving is tentatively scheduled for August 28.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    The Contractor will be topsoiling and street patching the week of August 18. Milling is tentatively scheduled for Friday, August 22. Paving is tentatively scheduled for August 28.
August 8, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Traffic remains shifted to the south side of 84th Street from France Avenue to Washburn Avenue and opened to one lane of traffic in both directions. Concrete work is complete in the Phase 2 area. Grading and placement of class 5 is complete in the Phase 2 area. The Contractor has been granted a noise exception for Saturday, August 9 to start at 7am and plans pave the first two layers of bituminous in the Phase 2 area (weather permitting). Boulevard restoration and placement of topsoil will follow the week of August 11. The Contractor plans to close Xerxes Avenue at W 84th Street starting Wednesday, August 13 for approximately 1 week to allow for reconstruction of the south side of W 84th Street at Xerxes Avenue. Traffic will remain open for eastbound and westbound W 84th Street during the closure and a detour will be provided for Xerxes Avenue that utilizes W 86th Street and Penn Avenue.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    The final layer of bituminous has been paved. Punch list work remains.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Boulevard restoration and placement of sod will continue the week of August 11.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Boulevard restoration and placement of sod will continue the week of August 11.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Concrete work, grading and placement of class 5 are complete. The first layer of bituminous has been paved. Paving of the bituminous driveways is anticipated to occur the week of August 11 along with boulevard restoration. The Contractor has been granted a noise exception for Saturday, August 9 to start at 7am and plans to prep bituminous driveways for paving and begin boulevard restoration.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Storm sewer work in this area is anticipated to complete the week of August 11. Grading and placement of class 5 will continue the week of August 11. Concrete work is anticipated to occur the week of August 11.
  • 14th Avenue (between E 96th Street and E 98th Street)
    Pavement removal and storm sewer work are anticipated to begin the week of August 11.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Tree removals have started in the area and will continue the week of August 11. Pavement removal is anticipated to begin on August 18.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Paving will be completed Friday, August 8. The Contractor anticipates striping Tuesday, August 12. Signal work will continue the week of August 11 along with sodding/seeding. The traffic signal at Little Rd will be on all way stop condition mid-week.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    Work has shifted to the north side of the road, all traffic is on the south two lanes. The Contractor will be completing concrete work the week of August 11 along with boulevard restoration and street patching. Street milling is tentatively scheduled for August 19 and paving August 22.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    The Contractor will begin removals the week of August 11 along with storm sewer work and concrete pouring.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    The Contractor will begin removals the week of August 11 along with storm sewer work and concrete pouring.
August 4, 2014

2014-102 PMP Street Maintenance Project

84th Street closure and detour
  • W. 98th Street closure
    Eastbound W. 98th Street will be closed from Normandale Boulevard to France Avenue starting 5 a.m. August 8 for paving with a detour provided that will utilize Normandale Blvd, W. 102nd Street and France Avenue. This phase is anticipated to last until 12 p.m. (noon). Once this phase is complete, westbound W. 98th Street will be closed from Normandale Boulevard to France Avenue for paving with a detour provided that will utilize Normandale Blvd, W. 102nd Street and France Avenue. This phase is anticipated to last through the early evening hours. Once paving is complete, all directions will be open to traffic.
August 1, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Traffic remains shifted to the south side of 84th Street from France Avenue to Washburn Avenue and opened to one lane of traffic in both directions. Concrete work has started in the Phase 2 area and is anticipated to complete by the end of the day, August 1. The Contractor has been granted a noise exception for Saturday, August 2 to start at 7am and plans to continue grading and placement of class 5. Grading and placement of class 5 will continue the week of August 4.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    Paving and striping are complete. Boulevard restoration has started and will continue the week of August 4.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Manholes and gate valves have been raised. The final layer of bituminous is anticipated to be paved either the week of August 4 or August 11.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Paving of the first layer of bituminous and driveways are complete. The Contractor has been granted a noise exception for Saturday, August 2 to start at 7am and plans to continue boulevard restoration and placement of topsoil. Boulevard restoration will continue the week of August 4 with sodding to follow later in the week.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Concrete work and paving of the first layer of bituminous are complete. Boulevard restoration and placement of topsoil is scheduled for the week of August 4.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Storm sewer work is complete. Grading and placement of class 5 has started and will continue the week of August 4. Concrete work has started in the area and will complete the week of August 4.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Pavement removal has started in this area and will continue the week of August 4. Storm sewer work is scheduled for the week of August 4.
  • Amsden Road (between West Bush Lake Road and Southwest Terminus)
    Street reconstruction work is anticipated to start in this area in mid-August.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy has completed work in the area. Street reconstruction work is anticipated to start in late August-early September in the area.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    Street milling will be completed Friday, August 1. The Contractor will raising iron and sodding/seeding the week of August 4. Work will continue on traffic signals at Little Road and France Avenue. Paving is anticipated for Friday, August 8.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    The Contractor will be completing concrete work on the south side the week of August 4 along with topsoiling and street patching. It is anticipated that the traffic will be switched to the south side lanes for work to begin on the north side later in the week.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    Work is anticipated to begin the week of August 11.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    Work is anticipated to begin the week of August 11.

July 2014

July 25, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    The Contractor has switched to Phase 2 which includes the westbound lanes of 84th Street from France Avenue to Washburn Avenue. Traffic has been shifted to the south side of 84th Street from France Avenue to Washburn Avenue and opened to one lane of traffic in both directions. The Contractor has been granted a noise exception for Saturday, July 26 to start at 7am and plans to begin storm sewer work in the Phase 2 area. Pavement removal in the Phase 2 area is complete. Grading and placement of class 5 in the area is scheduled for the week of July 28.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor is scheduled to pave the area on Friday, July 25, weather permitting. The Contractor will be striping the week of July 28 along with seeding and sodding.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    The Contractor plans to raise manholes and gate valves in preparation for the final layer of bituminous the week of July 28. Sod placement in the area is complete. The rain water gardens in this area will be completed and planted this Fall (Sept-Oct).
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Concrete work in this area is complete. Final grading of the class 5 in preparation for paving the first layer of bituminous is anticipated to complete by the end of this week. The Contractor is scheduled to pave the first layer of bituminous the week of July 28. Prepping and paving of bituminous driveways will follow later in the week of July 28.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Concrete work in the area has started and will complete the week of July 28. Final grading of the class 5 in preparation for paving the first layer of bituminous is scheduled for the week of July 28.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    Pavement removal in the area is complete. Storm sewer work has started and will complete early in the week of July 28. Grading and placement of class 5 will follow storm sewer work.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy will continue gas service replacement in the area the week of July 28.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    The Contractor anticipates starting pavement removal in this area later in the week of July 28 or the week of August 4.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be complete concrete work the week of July 28. Street patching along curb and topsoiling will be completed throughout the project area. Seeding and sodding will occur later in the week. Street milling is tentatively scheduled for August 4 (weather dependent) and paving is tentative scheduled for August 8 (weather dependent). Work on traffic signals will continue.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor is scheduled to pave the area on Friday, July 25, weather permitting. The Contractor will be striping the week of July 28 along with seeding and sodding.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    The Contractor will be removing curb and sidewalk on the south side the week of July 28. Concrete work will begin later in the week. The existing pedestrian traffic signal will be removed.
  • Bloomington Ferry Road (between Auto Club Road and Old Shakopee Road)
    City staff will be marking for removals the week of July 28.
  • Auto Club Road (between W. 114th Street and Bloomington Ferry Road)
    City staff will be marking for removals the week of July 28.
July 18, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Eastbound 84th Street is currently closed from France Avenue to Xerxes Avenue with a detour provided that utilizes France Avenue, American Boulevard and Penn Avenue. The Contractor has been granted a noise exception for Saturday, July 19 to start at 7am and plans to continue blvd restoration/topsoil placement on the south side of W 84th Street and complete raising of the manholes and gate valves in the closed area. The Contractor plans to switch to Phase 2 early in the week of July 21 (anticipating Tuesday, July 22) which includes the westbound lanes of 84th Street from France Avenue to Washburn Avenue. Traffic will then be shifted to the south side of 84th Street from France Avenue to Washburn Avenue and opened to one lane of traffic in both directions. Pavement removal in the Phase 2 area along with minor storm sewer work will follow the traffic switch later in the week of July 21.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be patching the street the week of July 21 along with topsoiling and boulevard restoration. The street will be milled on Tuesday, July 22 and paved Friday, July 25.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Paving of the bituminous driveways is complete. The Contractor has been granted a noise exception for Saturday, July 19 to start at 7 a.m. and plans to continue boulevard restoration in the area. Sodding has started in the area and will continue the week of July 21.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    The Contractor has been granted a noise exception for Saturday, July 19 to start at 7 a.m. and plans to continue concrete work between 82nd Street and 84th Street. Grading and placement of class 5 will continue the week of July 21. The Contractor anticipates paving the first layer of bituminous the week of July 28.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Grading and placement of class 5 is complete. Concrete work is anticipated to occur the week of July 21.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    The Contractor plans to begin pavement removal in this area early in the week of July 21. Storm sewer work will follow later in the week of July 21.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy will continue gas service replacement in the area the week of July 21.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    Gas service replacement is nearly complete in this area and is anticipated to complete the week of July 21. The Contractor anticipates starting pavement removal in this area later in the week of July 28 or the week of August 4.

84th Street closure and detour Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. The Contractor will be reconstructing the 84th Street in this location during the closure.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be begin removals in the median the week of July 21. Curb and other concrete work will be completed after removals. Street patching will be completed throughout the project area. Removals on the north side of the road between Rich Road and Normandale Blvd will continue along with concrete work.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor will be seeding/sodding the week of July 21.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will be patching the street the week of July 21 along with topsoiling and boulevard restoration. The street will be milled on Tuesday, July 22 and paved Friday, July 25.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    Traffic is anticipated to shift to the center lanes Friday, July 18. The Contractor will begin curb and sidewalk removals the week of July 21. Concrete work is anticipated to begin the end of the week of July 21.
  • Killebrew Drive (between T.H. 77 Ramp and Old Skakopee Rd)
    The Contractor will finish installing video detection system on the traffic signals at the intersection of Killebrew Drive and 24th Avenue the week of July 21.
July 11, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Eastbound 84th Street is currently closed from France Avenue to Xerxes Avenue with a detour provided that utilizes France Avenue, American Boulevard and Penn Avenue. The Contractor has been granted a noise exception for Saturday, July 12 from 7am-9am and plans to pave the first two layers of bituminous in the Phase 1 closed area 9 (weather permitting). Raising of the manholes and gate valves in this area is scheduled for the week of July 14 along with boulevard restoration and placement of topsoil. The Contractor plans to switch to Phase 2 by early in the week of July 14 which includes the westbound lanes of 84th Street from France Avenue to Washburn Avenue (weather permitting). Traffic will then be shifted to the south side of 84th Street from France Avenue to Washburn Avenue and opened to one lane of traffic in both directions.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be paving the base course of the right turn lane the week of July 14. Concrete work and topsoiling will continue throughout the project area. Work will begin on the pedestrian island and the pedestrian flashing beacon system at Thomas Avenue.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Paving of the first layer of bituminous is complete. Paving of the bituminous driveways is anticipated to complete early in the week of July 14. The Contractor has been granted a noise exception for Saturday, July 12 from 7am-9am and plans to begin boulevard restoration in the area and excavation for rain water gardens (weather permitting). Boulevard restoration will continue the week of July 14.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    The Contractor has been granted a noise exception for Saturday, July 12 from 7am-9am and plans to start concrete work in the area between 79 = Street and 82nd Street. Pavement and driveway removal is complete. Grading and placement of class 5 has started and will continue the week of July 14. Concrete work between 79 = Street and 82nd Street will continue early in the week of July 14. Storm sewer work is complete.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    Pavement and driveway removals along with storm sewer work are complete in the area. Grading and placement of class 5 and started and will continue the week of July 14.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    CenterPoint Energy has completed gas main and service installation in this area.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy will continue gas service replacement in the area the week of July 14.
  • 14th Avenue (between 96th Street and 98th Street)
    CenterPoint Energy has completed gas main installation and gas service replacement in this area.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    CenterPoint Energy has completed gas main installation in the area and gas service replacement will continue the week of July 14. The Contractor anticipates starting pavement removal in this area the week of July 21, depending on the status of the gas service replacement.

84th Street closure and detour Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. The Contractor will be reconstructing the 84th Street in this location during the closure.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be paving base course between Rich Road and Normandale Blvd the week of July 14. Concrete work, topsoiling, storm sewer installation and traffic signal work will continue throughout the project area. It is anticipated that traffic will switch to the south side of the road between Rich Road and Normandale Blvd Tuesday, July 15. Work will then begin on the north side of the road in that area.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor will be paving the base course of the right turn lane the week of July 14. Concrete work and topsoiling will continue throughout the project area. Work will begin on the pedestrian island and the pedestrian flashing beacon system at Thomas Avenue.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will be seeding/sodding and finish striping the week of July 14.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    The Contractor will begin storm sewer and sanitary sewer work the week of July 14. Traffic will be to the outside lanes while work begins in the middle of the road. It is anticipated that traffic will diverted to the north side of the roadway between the bridge and Humboldt Ave on Wednesday, July 16. The traffic is anticipated to shift to the south side of the roadway between the bridge and Humboldt Ave on Thursday, July 17. Storm sewer work will be completed during these shifts.
  • Killebrew Drive (between T.H. 77 Ramp and Old Skakopee Rd)
    The Contractor will be installing video detection system on the traffic signals at the intersections of Killebrew Drive and 24th Avenue the week of July 14.
July 3, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Eastbound 84th Street is currently closed from France Avenue to Xerxes Avenue with a detour provided that utilizes France Avenue, American Boulevard and Penn Avenue. Concrete work has started on the south side of W 84th Street in the closed area and is anticipated to complete by the end of the day Thursday, July 2. The Contractor will be fine grading class 5 in the area the week of July 7 in preparation for paving of the first layer of bituminous. This paving is anticipated to occur the week of July 14.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be installing storm sewer, finish street grading and installing curb and gutter on the south side of the street the week of July 7. Traffic will remain on the north side of the street.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Concrete curb and gutter and driveway placement is complete. The Contractor will be fine grading class 5 early in the week of July 7 and plans to pave the first layer of bituminous later in the week of July 7.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Pavement and driveway removal will continue the week of July 7 along with grading and placement of class 5. Storm sewer work has started in the area and will continue the week of July 7.
  • Harriet Avenue area (includes Harriet Avenue from W 93rd Street to South Terminus, Garfield Avenue from W 93rd Street to South Terminus)
    The Contractor plans to start pavement removals the week of July 7 in this area.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    CenterPoint Energy has completed gas main and service installation in this area.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy will continue gas service replacement in the area the week of July 7.
  • 14th Avenue (between 96th Street and 98th Street)
    CenterPoint Energy has completed gas main installation and will continue gas service replacement the week of July 7.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    CenterPoint Energy has completed gas main installation and will begin gas service replacement after the 14th Avenue area is complete.

84th Street closure and detour Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. The Contractor will be reconstructing the 84th Street in this location during the closure.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be pouring curb between Rich Road and Normandale Blvd the week of July 7. Other concrete work and topsoiling will continue throughout the project area. It is anticipated that traffic will be switched to the outside lanes Tuesday, July 8. The Contractor will then begin removals and storm sewer work on the inside lanes. Work on the traffic signals will continue.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will be seeding/sodding and finish striping the week of July 7.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    City staff will be surveying and marking for removals the week of July 7. Anticipated construction start is the week of July 14. Advance warning signs for construction will be installed Monday, July 7.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be installing storm sewer, finish street grading and installing curb and gutter on the south side of the street the week of July 7. Traffic will remain on the north side of the street.

June 2014

June 27, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Eastbound 84th Street is currently closed from France Avenue to Xerxes Avenue with a detour provided that utilizes France Avenue, American Boulevard and Penn Avenue. Pavement removal and utility work is complete in the closed area. The Contractor has started grading and placing class 5 and will continue the week of June 30. The Contractor has been granted a noise exception for Saturday, June 28 from 7am-9am and plans to continue grading and placing class 5. The bases for the new signal poles and cabinets have been poured.
  • W 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be finishing storm sewer work along with curb removal and beginning turn lane construction the week of June 30. Traffic will be diverted to the outside lanes Monday, June 30 for storm sewer work. Once this work is completed, all traffic will then shift to the north two lanes and work will begin along the south side of the street.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Concrete curb and gutter and driveway placement has started in the area and will complete early in the week of June 30 (weather permitting). The Contractor plans to grade and place class 5 later in the week of June 30 in preparation for the first layer of bituminous.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    Tree removal has started in the area and will continue the week of June 30. Pavement removal is scheduled to begin the week of June 30.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    CenterPoint Energy has started gas service replacement in the area and is anticipated to complete the week of June 30.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy has started gas service replacement in the area and will continue the week of June 30.
  • Portland Place area (includes Portland Place from 3rd Avenue to Portland Avenue, 4th Avenue from Portland Place to Old Shakopee Road)
    CenterPoint Energy has started gas main installation in the area and is anticipated to complete the week of June 30. Gas Service replacement will begin after the Portland Place area is complete.

84th Street closure and detour Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. The Contractor will be reconstructing the 84th Street in this location during the closure.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be pouring medians and continue street grading between Rich Road and Normandale Blvd the week of June 30. Concrete work and topsoiling will continue throughout the project area. Work on the signal systems will continue and new loops will be installed.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will be installing topsoil, seeding/sodding and pavement markings the week of June 30. Signal loops will be installed on Nicollet Avenue at the intersection with E. 84th Street.
  • W. 106th Street (between Xerxes Ave and Humboldt Ave)
    City staff will be surveying and marking for removals the week of June 30.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    This portion of W 84th Street is part of the 2014-102 PMP Street Maintenance Project. The Contractor will be finishing storm sewer work along with curb removal and beginning turn lane construction the week of June 30. Traffic will diverted to the outside lanes Monday, June 30 for storm sewer work. Once this work is completed, all traffic will then shift to the north two lanes and work will begin along the south side of the street.
June 20, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    Eastbound 84th Street is currently closed from France Avenue to Xerxes Avenue with a detour provided that utilizes France Avenue, American Boulevard and Penn Avenue. Westbound 84th Street will remain open to one lane during this phase. This phase is anticipated to last approximately 4-6 weeks. The Contractor has been granted a noise exception for Saturday, June 21 from 7 a.m. - 9 a.m. in this area and plans to remove pavement within the closed area. The Contractor has removed the signal poles at 84th Street/Xerxes Avenue and plans to excavate and pour bases for the new poles the week of June 23. The intersection is currently an all way stop and will remain for the duration of construction. Removals, grading and placement of class 5 gravel is scheduled to begin the week of June 23. Storm and sanitary sewer work is scheduled to begin the week of June 23 and will require a complete closure of W 84th Street between Beard and Chowen Avenue. This closure is scheduled to occur on Tues, 6/24 and Wed, 6/25 (weather permitting). A detour will be provided for the closure that utilizes France Avenue, American Boulevard and Penn Avenue.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    Tree removal in the area is complete. Storm sewer work in the area is complete. The Contractor has started grading and placing class 5 gravel and will continue the week of June 23. Concrete work may begin later in the week of June 23 (weather permitting).
  • 4th Avenue (between 84th Street and 79 ½ Street)
    CenterPoint Energy has completed work in this area. The Contractor anticipates starting pavement removal in the area the week of June 30.
  • Drew Avenue area (includes Drew Avenue from W 109th Street to W 110th Street, Ewing Avenue from W 109th Street to W 110th Street)
    CenterPoint Energy has completed gas main installation in this area. Gas service replacement is scheduled to begin the week of June 23.
  • Baillif Place area (includes Baillif Place from France Avenue to Xerxes Avenue, Ewing Avenue from Baillif Place to South Terminus, Drew/Chowen/Beard/Abbott Avenue from Baillif Place to Old Shakopee Road)
    CenterPoint Energy has completed gas main installation in the area. Gas service replacement is scheduled to begin the week of June 23.

84th Street closure and detour Storm and sanitary sewer work is scheduled to begin the week of June 23 and will require a complete closure of W 84th Street between Beard and Chowen Avenue. This closure is scheduled to occur on Tues, 6/24 and Wed, 6/25 (weather permitting). A detour will be provided for the closure that utilizes France Avenue, American Boulevard and Penn Avenue, similar to the current closure for eastbound W 84th Street.

2014-102 PMP Street Maintenance Project

  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will continue street grading between Rich Road and Normandale Blvd the week of June 23 along with finishing topsoiling. Construction on the bases for the new traffic signal at Collegeview will begin.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will be installing topsoil and raising manholes and gate valves the week of June 23. Milling is scheduled for June 24 and paving June 27 (weather depending).
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor will begin curb removal and pour curb on the north side the week of June 23 along with storm sewer work. Traffic will continue using the south two lanes.
June 13, 2014

2014-101 PMP Street Improvement Project

  • W 84th Street (between France Avenue and Washburn Avenue)
    The Contractor plans to start work in the area the week of June 16. The Contractor plans to excavate and pour concrete bases for the new signal poles at 84th Street/Xerxes Avenue the week of June 16. Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. Pavement sawcutting and removal are scheduled to follow the set-up of the closure later in the week with storm and sanitary sewer work to follow the week of June 23. This storm and sanitary work will require intermittent 1-2 day complete closures of W 84th Street, utilizing the same detour and more information will be given when a schedule is determined.
  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    CenterPoint Energy is complete in this area. Tree removal has started in this area and will continue the week of June 16. The Contractor is scheduled to begin pavement removals on June 16 followed by storm sewer work later in the week.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    CenterPoint Energy continues gas service installation in the area. The Contractor anticipates starting street reconstruction in the area in late June.

84th Street closure and detour Eastbound 84th Street will be closed from France Avenue to Xerxes Avenue starting June 19 with a detour provided that will utilize France Avenue, American Boulevard and Penn Avenue. This phase is anticipated to take approximately 1 month. Westbound 84th Street will remain open to one lane during this phase. The Contractor will be reconstructing the 84th Street in this location during the closure.

2014-102 PMP Street Maintenance Project

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    The Contractor anticipates completing sodding/seeding Friday, June 13.
  • Highwood Drive (between Bush Lake Road and West Terminus)
    The Contractor anticipates completing sodding/seeding Friday, June 13.
  • W. 78th Street (between France Avenue and Johnson Avenue)
    The Contractor anticipates completing sodding/seeding Friday, June 13.
  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will continue concrete work along with street grading, top soiling and traffic signal work the week of June 16. Street grading where watermain was installed will continue and paved after grading. The traffic signal at Collegeview Road will be removed Monday, June 16. The intersection will become an all way stop condition.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will begin concrete work along with raising manhole castings and top soiling the week of June 16. Milling and paving is planned for the week of June 23.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor plans to start work in the area the week of June 16 with storm sewer work, sanitary repairs and the removal of concrete. Lane closures and lane shifting will occur with the removals and utility work.
June 6, 2014

2014-101 PMP Street Improvement Project

A pre-construction meeting was held on Tues, June 3. The Contractor anticipates starting construction on the Project the week of June 16.

  • Upton Avenue area (includes Upton Avenue from W 106th Street to W 108th Street, Vincent Avenue from W 106th Street to W 108th Street)
    CenterPoint Energy has completed gas main installation in this area and has started replacing gas services. Service installation is anticipated to complete the week of June 9, weather permitting. The Contractor anticipates beginning removals in this area the week of June 16.
  • W 84th Street (between France Avenue and Washburn Avenue)
    CenterPoint Energy is scheduled to conduct minor service repairs in this area the week of June 9. The Contractor anticipates beginning removals in this area the week of June 16. The street reconstruction work on W 84th Street will involve closures along with associated detours. More information will be given when a schedule has been determined prior to construction.
  • 4th Avenue (between 84th Street and 79 ½ Street)
    CenterPoint Energy has completed gas main installation in this area. It is anticipated that gas main service installation will take an additional 2 weeks to complete.

2014-102 PMP Street Maintenance Project

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    The Contractor will be sodding/seeding the week of June 9 (weather permitting).
  • Highwood Drive (between Bush Lake Road and West Terminus)
    The Contractor will be sodding/seeding the week of June 9 (weather permitting).
  • W. 78th Street (between France Avenue and Johnson Avenue)
    Paving has been completed. Pavement marking will be installed the week of June 9. The Contractor will be sodding/seeding the week of June 9 (weather permitting).
  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will continue concrete work along with storm sewer installation and traffic signal work the week of June 6. Street grading where watermain was installed will begin. The Toledo Road and Little Road intersections will become 4 way stops mid week due to signal work.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    The Contractor will begin curb and street removals along with storm sewer and sanitary sewer work the week of June 6. Due to the sanitary sewer and storm sewer work, the intersection of 1st Avenue will be closed during working hours Tuesday and Wednesday and the intersection of 4th Avenue will be closed during working hours Thursday and Friday. These intersections will be opened at night.
  • W. 84th Street (between Washburn Avenue and Penn Avenue)
    The Contractor anticipates beginning work the week of June 16.

May 2014

May 30, 2014

2014-102 PMP Street Maintenance Project

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    All paving has been completed. The Contractor will be sodding/seeding the week of Monday, June 2nd.
  • Highwood Drive (between Bush Lake Road and West Terminus)
    Paving will be completed Friday, May 30th. The Contractor will be sodding/seeding the week of Monday, June 2nd.
  • W. 78th Street (between France Avenue and Johnson Avenue)
    The Contractor will be paving Monday, June 2nd (weather depending). Once paving is complete, the sodding/seeding will begin.
  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will be installing watermain between Normandale Boulevard and Rich Road the week of June 2nd. Water shutoffs will occur throughout the watermain construction and those affected will be notified. Curb and sidewalk removals will continue. New curb and sidewalk will be poured starting mid week.
  • E. 84th Street (between Nicollet Avenue and Stevens Avenue & between 2nd Avenue and Portland Avenue)
    City staff will begin marking curb and sidewalk for removals the week of June 2nd.
May 23, 2014

2014-102 PMP Street Maintenance Project

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    All concrete work and utility work has been completed. The Contractor will be begin street milling Tuesday, May 27 (weather permitting) along with raising manholes and gate valves to grade. Once the raising of manholes and gate valves are raised, bituminous paving will also begin Tuesday, May 27 (weather permitting).
  • Highwood Drive (between Bush Lake Road and West Terminus)
    All concrete work and utility work has been completed. The Contractor will be begin street milling Tuesday, May 27 (weather permitting) along with raising manholes and gate valves to grade. Once the raising of manholes and gate valves are raised, bituminous paving will also begin Tuesday, May 27 (weather permitting).
  • W. 78th Street (between France Avenue and Johnson Avenue)
    All concrete work and utility work has been completed. The Contractor will begin lowering manholes and gate valves for street milling the week of May 27th. The Contractor anticipates street milling and bituminous paving the week of June 2nd. Traffic control will be changing throughout construction.
  • W. 98th Street (between Normandale Blvd and France Avenue)
    The Contractor will begin curb and sidewalk removals the week of May 27th along with utility work. Traffic control for Phase 1 will be setup Tuesday, May 27th, middle lanes will be closed between Normandale Boulevard and Rich Road. This work consists of removing parts of the center median between Normandale Boulevard and Rich Road for traffic crossovers. Once these areas are removed and paved, traffic control will be switched over to Phase 2. During Phase 2, all traffic between Normandale Boulevard and Rich Road will be on the north two lanes of W. 98th Street. For Phase 2, the Contractor will be removing curb and working on utilities in this area. Temporary watermain will be setup along the south side of W. 98th Street near Normandale Boulevard. Traffic control will be changing throughout construction.
May 15, 2014

2014-102 PMP Street Maintenance Project

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    The Contractor will finish pouring concrete and raising manholes and gate valves along with beginning boulevard grading and street patching the week of May 19th. The Contractor tentatively plans on milling and paving the week of May 26th.
  • Highwood Drive (between Bush Lake Road and West Terminus)
    The Contractor will begin pouring concrete and raising manholes and gate valves along with boulevard grading the week of May 19th. The Contractor tentatively plans on milling and paving the week of May 26th.
  • W. 78th Street (between France Avenue and Johnson Avenue)
    The Contractor will be working on storm sewer and sanitary sewer structures along with lowering manholes and gate valves for milling the week of May 19th. Traffic control and lanes shifts will occur throughout the project.
  • W. 98th Street (between Normandale Blvd and France Avenue)
    City staff will begin marking curb and sidewalk for removals the week of May 19th. The Contractor plans on starting construction the week of May 26th.
May 9, 2014

2014-102 PMP Street Maintenance Project

A pre-construction conference was held Tuesday, May 6 at Public Works.

  • Pennsylvania Area (includes Autumn Chace Dr, Autumn Chace Cir, Rhode Island Ave, W. 83rd St, Pennsylvania Rd, W. 84th St, W. 84th St Cir, Oregon Rd, Maryland Rd, Oregon Cir, Nevada Cir, Maryland Cir)
    City staff has begun marking curb and sidewalk for removals. The Contractor began saw cutting curb and sidewalk on Thursday. The Contractor will begin storm sewer work and removals the week of May 12th.
  • Highwood Drive (between Bush Lake Road and West Terminus)
    City staff has begun marking curb and sidewalk for removals. The Contractor began saw cutting curb and sidewalk on Thursday. The Contractor will begin storm sewer work and removals the week of May 12th.
  • W. 78th Street (between France Avenue and Johnson Avenue)
    City staff will begin marking curb and sidewalk for removals the week of May 12th.

November 2013

November 27, 2013

2013-102 PMP Street Maintenance Project

  • W 98th Street Retaining Wall
    Installation of the fence on top of the wall is anticipated to occur in early December (weather permitting), if not this installation will occur in the Spring of 2014.
November 22, 2013

2014-101 PMP Street Improvement Project

Public information meetings for a portion of the streets on this project were held on November 19, 2013 at 2:00pm and 5:30pm in the Public Works Training Room. The public hearing at City Council is scheduled for Mon, December 2 for this portion of streets.

November 15, 2013

2014-101 PMP Street Improvement Project

The public hearing at City Council is scheduled for Mon, November 18 for a portion of the streets on this project. Public information meetings for the remainder of the neighborhoods on this project are scheduled for Tues, November 19 at 2:00 p.m. and 5:30 p.m. in the Public Works South Conference Room. The public hearing at City Council is scheduled for Mon, December 2. Mailings for these meetings have been sent out.

November 8, 2013

2014-101 PMP Street Improvement Project

A public hearing at City Council is scheduled for Monday, November 18 at 7:00 p.m. in the City Council Chambers for the neighborhoods that were included in the November 6 & 7 public information meetings.

November 5, 2013

2014-101 PMP Street Improvement Project

Public informational meetings are scheduled for Wednesday, Nov 6 at 2:00 p.m. and 5:30 p.m. and Thursday, Nov 7 at 5:30 p.m. in the Public Works Training Room for adjacent property owners.

 

For more information, contact:

Shelly Pederson, City Engineer
1700 W. 98th Street